Ekspansi Pabrik Flotasi Emas 2 Juta t/a di Xinjiang, China

Foto lokasi kasus

Cara Pemrosesan

  • Integration of a new crusher giratori primer to handle increased throughput.
  • Existing two-stage crushing circuit (Jaw + Cone Crusher) optimized and retrofitted to form a robust sistem penghancuran tiga tahap, memastikan ukuran umpan konsisten sebesar 12mm atau lebih kecil untuk penggilingan.
  • Installation of new, high-efficiency sel flotasi 200 m³ to form an expanded circuit.
  • Implementation of a “1-stage Rougher, 3-stage Cleaner, 2-stage Scavenger” configuration for superior selectivity and recovery.
  • Introduction of an advanced sistem dosis reagen otomatis to optimize collector and depressant usage, particularly for controlling arsenic.
  • DCentralized Sistem kontrol PLC/DCS integrated with the existing plant control room.
  • Addition of analis ukuran partikel online (PSD) and sensor pH/ORP for real-time process optimization, ensuring stable operation at the expanded capacity.
  • Addition of a second Φ5.0m x 8.5m Penggiling Bola operating in parallel with the existing unit.
  • Formation of a closed-circuit grinding system with hidroklasifier to achieve a target grind size of 80% passing 75µm, essential for liberating fine gold locked in sulfides.
  • New pengental laju tinggi for flotation concentrate dewatering.
  • Installation of a filter press for the concentrate to produce a low-moisture filter cake, reducing transportation costs.
  • Sistem pemompaan limbah yang ditingkatkan dan pipa ke fasilitas penyimpanan limbah yang ada, dirancang untuk menangani volume yang meningkat.
  • Lompatan Kapasitas: Successfully increased processing capacity by 800.000 t/tahun, mencapai target 2 Juta t/t.
  • Pemulihan Meningkat: Through finer grinding and optimized flotation, the overall gold recovery rate was significantly enhanced by 6.5%.
  • Kemampuan EPC Terbukti: Demonstrated strong capability in brownfield project execution, seamlessly integrating new systems with existing infrastructure with minimal disruption to ongoing production.
  • Diadaptasi untuk Bijih Refraktori: The flowsheet is specifically designed to tackle the challenges of refractory sulfide gold ores prevalent in the region.
  • Penekanan pada Efisiensi Ekologis: The expansion prioritized water recycling from the thickener overflow and dry tailing stacking where applicable, aligning with stringent environmental policies in Xinjiang.