Porject Case

2000 TPD Gold CIL Project in Africa

Raw Ore: Oxide Type Gold Ore
Gold Grade: 4 g/t
Gold Ingot Purity: 98%
Gold Recovery Rate: 97%
Capacity: 2000 tons per day
Work Scope: Equipment Supply and Installation Guidance

Visit by Appointment

Processing Way

3 stage crushing to make gold ore with size 12 mm below

2 stage ball mill grinding to obtain particle with size 74㎛ and D85

Centrifugal concentrator to recover the large size free gold

Cyanide destruction device is also equipped

Leaching system with 26 hours leaching time

Elution, desoprtion and electrolysis system and gold refinery system

Thickener and press filter for tailing dewatering and dry stacking

Project Cases

Related Equipment

Regarding the equipment used in the project construction cases.

View More