Raw Ore: Oxide and Sulfide Type Gold Ore
Gold Grade: 2.5 g/t
Final Product: Gold Bullion
Gold Recovery Rate: 91%
Capacity: 1200 tons per day
Work Scope: Ore Testing, Engineering Design, Equipment Supply, and Installation Guidance
Here are some photos of the project, click on the small picture to view the large picture.
Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.
Three-stage crushing circuit to reduce ore size below 10 mm
Gravity concentration by centrifugal concentrator to recover coarse free gold
Elution, electrowinning, and smelting system for gold bullion production
Two-stage ball mill grinding to achieve liberation particle size of 74μm and D80
“Leaching & Adsorption” system (CIL) with 24-hour retention time
Thickener and filter press for tailings dewatering and dry stack disposal
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195
Address: No.2555,Xiupu Road, Pudong, Shanghai
Copyright © 2023. Prominer (Shanghai) Mining Technology Co.,Ltd.