Raw Ore: Sulfide-Refractory Gold Ore (25% Sulfide)
Gold Grade: 2.8-4.1 g/t
Final Product: 99.99% Gold Ingot
Gold Recovery Rate: 93.5% (CIL Yield: 91.2% + Gravity: 2.3%)
Capacity: 3000 tons per day
Work Scope: EPC + 2-Year Optimization
Here are some photos of the project, click on the small picture to view the large picture.
Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.
Crushing: 3-stage to ≤12mm (SAG mill feed optimization)
Grinding: SAB circuit (SAG + Ball mill → P80=75μm)
Carbon Stripping: AARL process (98.5% stripping efficiency)
Pre-concentration: XRT sorting discard 15% waste (Gold loss <0.5%)
Gravity Recovery:3x Knelson KC-XD72 (Recovery: 52% of free gold)
Electrowinning: 94% current efficiency → Cathode slime Au≥40%
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195
Address: No.2555,Xiupu Road, Pudong, Shanghai
Copyright © 2023. Prominer (Shanghai) Mining Technology Co.,Ltd.