Raw Ore: Sulfide-Type Gold Ore (Pyrite and Arsenopyrite bearing)
Gold Grade: 4.2 g/t
Final Product: Gold Dore Bar
Gold Recovery Rate: 92%
Capacity: 500 tons per day
Work Scope: EPC (Engineering, Procurement, Construction & Commissioning)
Here are some photos of the project, click on the small picture to view the large picture.







Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.


3-stage Crushing and Screening to reduce ore size to below 12mm

Pre-flotation concentration using a bank of Jameson Cells to produce a sulfide concentrate

Elution, Electrowinning & Gold Smelting Furnace for dore bar production

Tailings dewatering via thickener and filter press for dry stack disposal

SABC Circuit (SAG Mill + Ball Mill) for grinding to P80 of 75µm

CIL (Carbon-in-Leach) Circuit with 24-hour retention time for gold leaching

Cyanide Detoxification system (INCO SO2/Air) for tailings treatment

Click the button below for more details
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195
Address: No.2555,Xiupu Road, Pudong, Shanghai
Copyright © 2023. Prominer (Shanghai) Mining Technology Co.,Ltd.