Raw Ore: Sulfide-Bearing Gold Ore (30% Sulfide)
Gold Grade: 3.2 g/t
Final Product: 98.99% Gold Ingot (London Good Delivery)
Recovery Rate: 92%
Capacity: 700 tons per day
Work Scope: Full EPC + Automation System
Here are some photos of the project, click on the small picture to view the large picture.
Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.
Primary Crushing:Jaw crusher → Cone crusher → Ore size ≤15mm
Gold Recovery:Carbon elution (Zadra process at 130°C);Electrowinning cells (98% Au deposit on cathodes)
Environmental Management:Tailings paste plant (75% solids dry stacking)
Pre-concentration:Knelson concentrators recover 40% free gold (>0.1mm)
Oxidation & Leaching: Dual CIL tanks (24hrs leaching with NaCN)
Refining to Pure Gold: Induction furnace smelting (1200°C); Miller chlorination (99.5% purity); Wohlwill electrolysis (99.99% purity)
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195
Address: No.2555,Xiupu Road, Pudong, Shanghai
Copyright © 2023. Prominer (Shanghai) Mining Technology Co.,Ltd.