Raw Material: Carbon-slag from aluminum electrolysis
Feed Grade: 15–20% Cryolite content
Final Product: Recycled Cryolite ( purity ≥ 92% )
Project Capacity: 3 tons per hour ( stably achieving 150 tons per day )
Project Type: Circular Economy & Resource Recovery
Work Scope: Process Design, Equipment Supply, Installation Guidance, On-site Optimization
Here are some photos of the project, click on the small picture to view the large picture.







Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.


Crushing & Screening System – Customized upgrade to handle variable material conditions and improve liberation of cryolite from carbon-slag

Flotation System – 1 stage rougher, 2 stage cleaner flotation to recover high-purity cryolite

Tailing Treatment – Dewatering and dry stacking for environmental compliance

Ball Mill Grinding – Achieve suitable particle size for flotation feed

Concentrate Dewatering – Thickener + Press filter for final cryolite product

Direct Reuse – Recovered cryolite returned to aluminum electrolysis process, reducing raw material cost and waste discharge
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195
Address: No.2555,Xiupu Road, Pudong, Shanghai
Copyright © 2023. Prominer (Shanghai) Mining Technology Co.,Ltd.