Raw Ore: Multi-metal sulfide ore (Cu, Zn, Au)
Ore Grade: Cu 1.2%, Zn 2.5%, Au 1.5 g/t
Recovery Rate: Cu 92%, Zn 88%, Au 85%
Capacity: 800 tons per day
Work Scope: EPC (Engineering, Procurement, Construction) including civil, mechanical, and infrastructure works
Here are some photos of the project, click on the small picture to view the large picture.







Below are some ways to handle this plan. If you want to get a more detailed plan, please click the button to contact us.


Underground and open-pit ore haulage and primary crushing system

2-stage ball mill grinding to achieve particle size of 75 µm and D80

Concentrate thickening, filtering, and packaging system

Integrated civil works for plant infrastructure and access roads

PLC-based automated control and monitoring system

3-stage crushing and screening to reduce ore size below 15 mm

Bulk flotation and sequential Cu-Zn separation flotation circuits

Tailings dam design and dry stacking system for waste management

Mechanical installation of conveyors, pumps, and processing equipment
To find out more about our products and solutions, please fll out the form below and one of our experts will get back to you shortly
3000 TPD Gold Flotation Project in Shandong Province
2500TPD Lithium Ore Flotation in Sichuan
Fax: (+86) 021-60870195